Noise Control Product and Submittal Lead Times
Updated: November 11/17/26
ALL Plants work on a 4 day Schedule Monday – Thursdays, closed Fridays
Closures Nashville:
Thanksgiving November 26th 2026
Yearly Inventory December 10th – 11th 2026
Dec shut down 12/23 to 12/24 , 12/31 , 1/1/27
Toronto
Yearly Inventory December 17th – 18th 2026
Dec shut down 12/24 to 1/1/27
NOISE CONTROL STANDARD PRODUCTS
| Options | Description | Min Lead Time |
|---|---|---|
| Non-Standard | Rectangular or circular flanges, windows & doors, CD with centerbody, transitional silencers, Plenum | 8-10 weeks |
| Special Finishes | Powder coating, hot-dip galvanizing, special paint specifications | 10-12 Weeks |
| Non-Galvanized Materials | Stainless steel, Aluminum, Satin coat | 10-12 Weeks |
| Special Materials | Stainless steel with PVC coating, G165, and other specialty materials, Special | Contact Factory |
| Architectural Grade Louvers (Release $ Net) | Lead Time |
|---|---|
| Under $20,000 (Non-Painted) | 8-10 weeks |
| Under $20,000 (Painted) | 8-10 weeks |
| Over $20,000 | 10-12 weeks |
| Option: with Kynar or special paint colour | Add 2 weeks to the above lead times |
NOTES
- All product lead times start aging after written confirmation of release.
- Use the longest lead time when quoting multiple product types.
- All clean releases placed after 2:00PM Est aging starts the next working day.
- Weeks with a + indicates starting weeks with subsequent shipments 2-3 weeks apart.
CURB PRODUCTS
NOTES
- All product lead times start aging after written confirmation of release.
- Use the longest lead time when quoting multiple product types.
- All clean releases placed after 2:00PM Est aging starts the next working day.
SUBMITTALS
Noise Control Submittals
| Product | Submittal Lead time (days) | Re Submittal Lead time (days) |
|---|---|---|
| Standard silencers: RD, RFL, RNM, CD, CFL, CFM, CENM, RED, REFL, RENM, SRD | 5 | 5 |
| Non-standard silencers: TFL, TNM, RLP, CLP, RSB, RDS, EX-RD, EX-RFL, EX-RNM, EX-RED, EX-REFL, EX-RENM, AC | 8 | 5 |
| Plenums, Enclosures and Barrier Walls | 13 | 8 |
| Acoustical Louvers | 13 | 7 |
| Sil-Throw | 13 | 7 |
Curb Submittals
| Product | Scope (QTY) | Submittal Lead time (days) | Re Submittal Lead time (days) | ||
|---|---|---|---|---|---|
| Seismic/Non-Seismic | Calculations | Seismic/Non-Seismic | Calculations | ||
| RC curb (standard) (# of curbs) | 2 | 5 | 7 | 5 | 7 |
| 6 | 6 | 9 | |||
| 10 | 8 | 11 | 6 | 8 | |
| 16 | 10 | 13 | |||
| RTR (# of RTRs) ARTR (# of ARTRs) | 2 | 5 | 7 | 5 | 7 |
| 6 | 6 | 9 | |||
| 10 | 8 | 11 | 6 | 9 | |
| 16 | 10 | 13 | |||
| Standard VCR Curbs (# of VCRs) | 2 | 5 | 7 | 3 | 5 |
| 6 | 7 | 8 | 4 | ||
| 10 | 9 | 10 | 5 | 6 | |
| 16 | 11 | 12 | 9 | ||
| CDN Seismic Curb Calcs | Any | ― | Add 3 days to above | ― | Add 3 days to above |
| Product | Scope (QTY) | Submittal Lead time (days) | Re Submittal Lead time (days) |
|---|---|---|---|
| Special VCR curbs, priced with a special estimate | Any | 13 working days | 7 working days |
NOTES
- All submittals lead times start aging after receipt of required information. See Appendix A.
- Re-submittal lead times start aging after receipt of a revised purchase order (if changes result in added costs).
- Use the longest lead time when quoting multiple submittal types.