Noise Control Product and Submittal Lead Times
Updated: April 12th 2024
Note:
All Plants work on a 4 day schedule Monday – Thursday, closed Fridays.
Closures:
Toronto Location
Victoria Day Holiday May 20th 2024
Canada Day July 1st 2024
Nashville location
Memorial Day May 27th 2024
Juneteenth Holiday 19th 2024
Independence Day July 4th 2024
NOISE CONTROL PRODUCTS
Architectural Grade Louvers (Release $ Net) | Lead Time |
---|---|
Under $20,000 (Non-Painted) | 8-10 weeks |
Under $20,000 (Painted) | 8-10 weeks |
Over $20,000 | 10-12 weeks |
Option: with Kynar or special paint colour | Add 2 weeks to the above lead times |
NOTES
- All product lead times start aging after written confirmation of release.
- Use the longest lead time when quoting multiple product types.
- All clean releases placed after 2:00PM Est aging starts the next working day.
CURB PRODUCTS
Standard Items | Scope (QTY) | Manufacturing Lead Times |
---|---|---|
RC Curbs (Standard) VCR Curbs (Standard) RTR Rails (Standard) ARTR Rails (Standard) | 2 | 2–3 weeks |
6 | 3–4 weeks | |
10 | 4–5 weeks | |
16 |
NOTES
- All product lead times start aging after written confirmation of release.
- Use the longest lead time when quoting multiple product types.
- All clean releases placed after 2:00PM Est aging starts the next working day.
SUBMITTALS
Noise Control Submittals
Product | Submittal Lead time (days) | Re Submittal Lead time (days) |
---|---|---|
Standard silencers: RD, RFL, RNM, CD, CFL, CFM, CENM, RED, REFL, RENM, SRD | 5 | 5 |
Non-standard silencers: TFL, TNM, RLP, CLP, RSB, RDS, EX-RD, EX-RFL, EX-RNM, EX-RED, EX-REFL, EX-RENM, AC | 8 | 5 |
Plenums, Enclosures and Barrier Walls | 13 | 8 |
Acoustical Louvers | 13 | 7 |
Sil-Throw | 13 | 7 |
Curb Submittals
Product | Scope (QTY) | Submittal Lead time (days) | Re Submittal Lead time (days) | ||
---|---|---|---|---|---|
Seismic/Non-Seismic | Calculations | Seismic/Non-Seismic | Calculations | ||
RC curb (standard) (# of curbs) | 2 | 5 | 7 | 5 | 7 |
6 | 6 | 9 | |||
10 | 8 | 11 | 6 | 8 | |
16 | 10 | 13 | |||
RTR (# of RTRs) ARTR (# of ARTRs) | 2 | 5 | 7 | 5 | 7 |
6 | 6 | 9 | |||
10 | 8 | 11 | 6 | 9 | |
16 | 10 | 13 | |||
Standard VCR Curbs (# of VCRs) | 2 | 5 | 7 | 3 | 5 |
6 | 7 | 8 | 4 | ||
10 | 9 | 10 | 5 | 6 | |
16 | 11 | 12 | 9 | ||
CDN Seismic Curb Calcs | Any | ― | Add 3 days to above | ― | Add 3 days to above |
Product | Scope (QTY) | Submittal Lead time (days) | Re Submittal Lead time (days) |
---|---|---|---|
Special VCR curbs, priced with a special estimate | Any | 13 working days | 7 working days |
NOTES
- All submittals lead times start aging after receipt of required information. See Appendix A.
- Re-submittal lead times start aging after receipt of a revised purchase order (if changes result in added costs).
- Use the longest lead time when quoting multiple submittal types.